Harlem Road  
 

Harlem Road

 
Fort Bend County , Texas  
   
Summary/Benefits  
Evaluated existing and alternative alignments for the schematic design of Harlem Road to improve safety, relieve traffic congestion and improve regional mobility.
   
Project Elements
7.4-mile Route Analysis and Schematic Design
Roadway Geometrics
Typical Sections
Schematic Design
Public Meetings
Hydrologic/Hydraulic Analysis
Phase I Environmental Site Assessment
Surveying
Abstracting / Maps
Right-Of-Way Mapping
Controlled Aerial Photography
Digital Terrain Model (DTM)
Utility Research, Meetings, and Coordination
Traffic Analysis
Accident Analysis
Pavement Design
Construction Cost: $14.5 Million
   
TxDOT Categories
3.2.1, 4.2.1, 7.1.1, 10.1.1, 15.1.1, 15.1.2, 15.1.3, 15.1.4, 15.2.1, 15.4.1
   
Description
Route study and schematic design for a 7.4-mile corridor along Harlem Road. Project included alternate route determination, functional
Harlem Road
classification and design criteria determination, drainage analysis, cost estimates, and utility investigation. Typical sections were developed utilizing both Texas Department of Transportation (TxDOT) and Fort Bend County design criteria. Curb and gutter, open ditch, and curb and gutter with open ditch combinations were developed and considered.
   
An opinion of probable cost and preliminary hydraulic calculations were performed for each alternative. Relocations, right-of-way, floodplains, and environmental impacts provided additional route selection criteria. The schematic layout utilized digital aerial photographs taken for this project.